Software Release Note for core version 10.7.0

(click here for SRN history)

Author: Mathijs Homminga [mathijs.homminga@rssd.esa.int]
Date: 06-01-2005
Summary: Several SPRs fixed plus many SCREWs implemented (example: split observation functionality added)

Dependencies

System name ID Version
ISOC Database DB 4.1.4 (new)

Fixed SPRs:

PHS:

SPR 636 The value of the parameter is not checked during typing but only after pressing enter or committing the observation.
SPR 637 The flux is now printed correctly.
SPR 643 The start and end point limits of GCDE patterns are now determined dynamically.

OSS:

SPR 638 The fixed time observations are now correctly ordered based on their starting time.
SPR 640 A warning is shown when the user attempts to unschedule a revolution that is earlier than one that is not currently unscheduled. The user should always unschedule the later revolution first. This warning will also appear if the user attempts to unschedule the last revolution when rev n+1 has also been loaded (which is always the case if it exists in the database). In this cased the user should ignore the warning.

Implemented SCRs:

POS Checker:

SCR 410 Implemented as proposed

PHS:

SCR 427 The approved duration is adjusted automaticaly when the start and/or end pointings are changed (and the observation is commited)
SCR 431 You can now split an observation. Splitting an observation is similar to copying it, except that the durations and start- and endpointings are handled correctly. One can only split (partly) scheduled observations. The system keeps a link between the splitted observations (no need to copy parent observations)

OSS:

SCR 428 When a user wants to reschedule a revolution, the system shows a pop-up dialog asking if the user wants to freeze the GS handovers.
SCR 449 The IFTS source (SAC/SOC) is now configurable (isocx.ifts.source property).

Other changes/comments: